During the deployment: onboarding, build and go-live

Provisioning, the timeline from signature to handover, the onboarding form and when each input is due, identity and communications, the migration cockpit, cutover, and the go-live gates.

Provisioning in three steps

StepWhat happens
1 — Proposal & contractThe customer configures cloud, region, nodes, database, DR and environments; audited revenue is provided; the main technical contact is named in the contract.
2 — BuildThe onboarding form is submitted; kick-off fixes milestones, responsibilities and the timeline; environments are built from infrastructure-as-code.
3 — HandoverAccess goes to the technical contact; the customer verifies connectivity and SSO; configuration and migration begin.

Build starts only after signature, audited revenue and the onboarding form have all arrived. Start the customer’s network and DNS work in parallel with contracting — it is usually the longest lead item.

Timeline (proposed default, working days)

FromToWhoTarget
Contract signedOnboarding form submittedCustomer5 working days
Onboarding formDesign sign-offTRANXACT5 working days
Design sign-offCommitted handover dateTRANXACT5 working days, +5 with Live DR (TO_4.1.01)

Private connectivity, customer-managed keys and extra environments can extend the build. Configuration, migration and testing follow the handover and are planned per module scope.

Commit a go-live date only after the handover date is fixed and the migration plan is sized.

The onboarding form

InputDescriptionWhen
Cloud provider & regionsAWS, Azure or Google Cloud; primary and Live DR regionsBefore signing
Runtime sizingWorker node size and count (3 minimum); environmentsBefore signing
DatabaseEngine of choice and size (HA)Before signing
Continuity patternAvailability tier, Live DR region, vault retention, RPO/RTOBefore signing
Modules & scopeModules at go-live, legal entities, currencies, languagesBefore signing
Compliance flagsRegulated data (health, education, payroll), retentionBefore signing
ASK AIEngine tier or BYOK, processing region, usage budgetBefore signing
NetworkPrivate /22 ranges (and DR), connectivity option, egress allow-listWithin 5 working days of kick-off
DNS & certificatesFQDN, DNS owner, public-CA certificateWithin 5 working days
IdentityIdP for SSO, admin users, MFA policyWithin 5 working days
IntegrationsBank, payroll, tax, BI and legacy endpointsWithin 5 working days
ContactsTechnical, network, security, finance, data migration; two 24×7 contactsWithin 5 working days

Submitting it is the customer’s task (MIG_8.5.01). Missing inputs delay the committed handover date. Most inputs map straight to the configurator, so reuse the customer’s configuration PDF to pre-fill it.

  • Fixed once the build starts: region, address ranges, FQDN, database engine.
  • Ranges must not overlap any customer, partner or landing-zone network, including the Live DR region.
  • The technical contact should be an IT lead who can act on credentials and network changes — not a CxO, finance or procurement contact (MIG_8.5.03).
  • Changes after submission go through the Orchestrator and are logged as non-standard or change requests.
  • Track every open input in the fortnightly operations sync until handover.

Identity and communications

  1. Welcome pack and kick-off invitation after signature (MIG_8.5.02).
  2. Kick-off (SM_1.1.01): the support manual and service portal, landscape and scope, and a walk through the R&R workbook, RACI and escalation matrix.
  3. SSO federation with the customer IdP over SAML 2.0 or OIDC (PLAT_5.6.01); SCIM provisioning if wanted (PLAT_5.6.05).
  4. Role mapping, tested with real users before data migration starts.
  5. Access reviews scheduled from go-live (PLAT_5.6.04, Excluded).
  • All communication goes to the named technical contact; credentials go only to them (TO_4.1.02). A deputy may be named on the form.
  • Operational emails — incidents, maintenance, releases — go to the technical contact and the 24×7 contacts.
  • Allow-list TRANXACT sender domains so provisioning and alert emails are not quarantined (PLAT_5.5.03).
  • A missing email: check spam and quarantine first, then raise a request in the service portal.
  • An SSO problem: confirm the IdP metadata, the claim mapping and the test user’s role before raising an incident.

The migration cockpit

  1. Extract — from legacy systems and spreadsheets (MIG_8.3.01, customer).
  2. Map — to TRANXACT entities, accounts and master data; cleanse (MIG_8.3.02, customer).
  3. Validate — rules, duplicates, missing data (MIG_8.2.01, TRANXACT).
  4. Trial loads — into non-production, repeated (MIG_8.2.01; loads beyond the agreed cycles are Additional, MIG_8.2.02).
  5. Reconcile — trial balance, sub-ledgers, stock; sign off opening balances (MIG_8.3.03, customer).
  6. Cutover — freeze, final load and technical verification (MIG_8.4.03, TRANXACT), after the customer’s go / no-go (MIG_8.4.02).

TRANXACT provides the cockpit and load templates (MIG_8.1.01), the migration plan (MIG_8.1.02) and the cutover plan and freeze window, prepared jointly (MIG_8.4.01).

Data quality, not tooling, sets the go-live date. Every opening balance reconciles to the audited source before go-live, and that sign-off is the customer’s.

Checklist: signature to go-live

Within 5 working daysBuildHandoverGo-live readiness
Onboarding form completeVPN / private link upAccess verifiedMigration reconciled
Technical contact namedDNS and certificate liveMonitoring dashboard sharedIntegrations tested
Egress allow-list draftedSSO and roles mappedVault copies landingLive DR switchover passed
Contacts per area, two 24×7Environments built (IaC)Live DR lag within targetClean-room restore passed

After go-live, hypercare — extended support with daily check-ins, typically 4–8 weeks — is available as the H1 package (PKG_7.6.01).

Values marked proposed default are the deployment guide’s recommended starting points. Confirm each one per customer; the contract, order form, SLA and DPA prevail over this page.