T-Minus: adoption and change

Coaching in the flow instead of the classroom, the adoption journey per user, role readiness, the see-it / do-it / own-it change model, change impact, stakeholders, communications, and meeting resistance.

Coach in the flow, not the classroom

Big-bang trainingT-Minus
Weeks of classroom sessions before go-liveKey users learn by discovering and configuring their own tenant
Generic scenarios, forgotten by T+1Everyone learns by rehearsing their own real day
Manuals that age on day oneThe queue shows each user what needs attention; ASK answers "how do I…" by doing it with them, under their permissions
Training measured in hours attendedAdoption measured by work done

Replace the training plan with an adoption plan. The measure is not hours trained but users who completed their rehearsal tasks and their first real week unaided.

The adoption journey per user

WhenWhoWhat
T-27 → T-18Key usersPlay their roles in discovery; shape the Fit Ledger
T-17 → T-11Key usersCo-drive configuration; own their role design
T-9 → T-5All usersLog in, see their own queue, try their own tasks on test data
T-2 → T-1All usersRun their real day in the rehearsal
T+1 → T+30All usersReal work with the queue and ASK; hypercare on exceptions

Every user meets the system in their own role at least twice before go-live. Readiness measure: the share of T+1 users who completed their rehearsal tasks in their own role — target 95% or more. Key users are the multipliers: each should coach three to eight colleagues through the rehearsal; name them in the adoption register at T-27.

Role readiness (proposed default)

One line per user in the Toolkit’s Role & Adoption Readiness sheet, with four checks — queue configured, ASK enabled, logged in by T-5, rehearsed by T-1 — and a named buddy where needed. The sheet calculates Ready and rolls readiness up per role and department.

Anyone not ready at T-1 gets a named buddy — a key user — for their first week, rather than a go-live delay.

Change on the countdown: see it, do it, own it

StageWhenWhat happens
See itT-27 → T-11Why we are changing and the go-live date, from the executive sponsor; each team sees its future screens in the tenant; change impact captured per role
Do itT-10 → T-1Users log in and try their own tasks; everyone runs their real day in the rehearsal; concerns logged and answered in the standup
Own itT-0 → T+30Queue and ASK in daily work; legacy read-only, so old habits are retired; wins shared; same-week configuration changes prove responsiveness

A change model sized for 27 days instead of 12 months: direct experience of the new system replaces most awareness-building, so keep messages short and screen-based.

Change impact assessment (examples)

ProcessTodayWith TRANXACTRolesImpactChange action
Order to cashRe-keyed from CRM to ERP; credit checked after shippingOne flow; credit hold before shippingSales, billing, creditHighRehearse credit-hold scenarios; a queue rule
Month-end closeSpreadsheets stitch four systemsClose from one ledger with a checklistFinanceHighController-led walkthrough in the tenant
Purchase approvalE-mail approvalsApproval flow in the queueBudget holdersMediumOne-page guide; an ASK prompt
Stock countsOvernight copy, never currentLive stockWarehouseMediumShow live stock in the rehearsal
PayslipsPaper / PDF by e-mailSelf-serviceAll employeesLowComms at T-5 and T+1

Rate impact on the people, not the process: a small change for a large team can outweigh a big change for one specialist.

Stakeholders and champions (proposed default)

QuadrantWho
Manage closely — high influence, high impactCFO, COO, Countdown Owner, finance controller
Keep satisfied — high influence, lower impactCEO, board sponsor, IT director, auditors
Keep engaged — lower influence, high impactClerks, warehouse, sales, payroll teams
Keep informed — lower influence, lower impactWider staff, partners, customers, suppliers

Every high-influence, high-impact stakeholder attends at least one standup and the rehearsal. Champions come from the key-user list, one per team.

Communications on the countdown (proposed default)

T-dayAudienceMessageChannelFrom
T-27All staffWe go live on [date]: why, what, and the countdownTown hall / e-mailExecutive sponsor
T-18Affected teamsWhat is in wave 1 and what comes in T-PlusTeam meetingsCountdown Owner
T-10All usersYour login, your screens, your rehearsal slotE-mail + tenantAdoption Navigator
T-3Customers & suppliersNew invoice layouts; bank details unchangedLetter / e-mailFinance
T-1All usersRehearsal result, the GO decision, freeze timeE-mail / chatCountdown Owner
T-0All staffWe are live: first invoice posted; where to get helpChat / intranetExecutive sponsor
T+5 / T+30All usersWins, fixes delivered, what is next in T-PlusNewsletterFlight Lead

Every message answers "what changes for me, and when". Send from the executive sponsor or the Countdown Owner, never from the project mailbox alone.

Resistance, and how to meet it

What people sayWhat is behind itThe T-Minus answer
"27 days can’t be enough"Experience of long ERP projectsShow the four removed phases and the countdown board; invite them to a standup
"We’ll lose our reports"Fear of losing controlA Fit Ledger line per report; most become dashboards or "not needed"
"Nobody trained us"Training = classroomTheir rehearsal slot and ASK; a buddy for the first week
"The old system did X"HabitRule 2: show the screen; configure, T-Plus or no
"What about history?"Audit worryThe legacy archive stays queryable; period balances where needed
"Too busy for the project"Day-job pressureThe Countdown Owner releases key users; the rehearsal is their real work

Log recurring objections in the RAID log as risks. If one role keeps raising the same point, it is usually a missing Fit Ledger line, not resistance.