T-Minus: go-live, hypercare and T-Plus

What happens on T-0, hypercare from daily to absorbed, T-Plus waves, the artifact catalogue, using the Project Plans workbook, and the deployment checklist from pre-flight to hypercare exit.

T-0: the rehearsed cutover, for real

  • Legacy frozen and set read-only at the agreed cut-off time.
  • The final Migration Cockpit load — a repeat of the timed dry run.
  • Trial balance reconciled and signed by the finance controller.
  • Integrations switched to production endpoints.
  • Users log in; the first invoice posts in production, usually before lunch.

Artifacts: the Cutover Runbook’s final column, the signed reconciliation, the Hypercare Exception Log opened, and the KPI days-to-first-posted-invoice. See Mock loads, reconciliation and the cutover runbook for the hour-by-hour sequence.

Keep the legacy archive queryable after it goes read-only. Rule 4 depends on history staying available without being migrated.

Hypercare: from daily to absorbed (proposed default)

WhenCadenceFocus
T+1 → T+10Daily 15-minute standupYesterday’s exceptions, fixes, same-day configuration changes
T+11 → T+20Twice weeklyTrends; preparing the first month-end close
T+21 → T+30AbsorbedThe normal operations rhythm; T-Plus wave planning
Exception typeExampleHandled by
Posting or reconciliationUnmatched bank line, suspense balanceFinance key user + Ledger Architect
User cannot complete a taskMissing permission, unclear stepAdoption Navigator (ASK, role fix)
Integration message failedBank file rejectedOps Pilot + partner
Configuration change requestA new approval levelLedger Architect, the same week

Close hypercare on evidence, not on a calendar date: exceptions below threshold for five working days, the first month-end closed in TRANXACT, and no open critical or high defects.

How this fits the service contract: T-Minus hypercare, T+1 to T+30, is part of the method. Extended post-go-live support with daily check-ins for an agreed period — typically 4 to 8 weeks — is the separately contracted Hypercare package (H1) in the Roles & Responsibilities workbook. After hypercare, the steady-state service described in After go-live: running the service takes over.

T-Plus waves (proposed default)

T-Plus backlog from the Fit Ledger → prioritise with the Countdown Owner → a mini-countdown per wave → rehearse the change → toggle on.

Source of scopeWhat it adds
Deferred Fit Ledger linesEvery T-Plus line from wave 1, prioritised by value
More entities and regionsAdditional legal entities, currencies and languages
More modulesManufacturing, EHR, Student Lifecycle, HRMS as toggles
Period and archive follow-upsAdditional period balances if a new report needs them

Plan the first T-Plus wave before hypercare ends, while the countdown team is still together; each wave reuses the same Fit Ledger, plans and artifacts. Growth never triggers a re-implementation, and the measure is modules live per quarter without one.

The artifact catalogue

ArtifactCreatedOwnerWhere
Countdown project plan (per source system)T-27Flight LeadProject Plans · one sheet per source
Pre-flight & deployment checklistPre-flightFlight LeadToolkit · Deployment Checklist
Fit LedgerT-27 → T-18Countdown OwnerToolkit · Fit Ledger
Migration scope decision & object registerT-24Migration ConductorToolkit · Migration Scope, Object Register
Configuration workbookT-17 → T-11Ledger ArchitectToolkit · Configuration Workbook
Test plan & scriptsT-17Ledger ArchitectToolkit · Test Plan
TB & sub-ledger reconciliationsT-10 → T-0Finance controllerToolkit · TB Reconciliation, Sub-ledger Recon
Cutover runbookT-8Migration ConductorToolkit · Cutover Runbook
Rehearsal script & go / no-go gateT-5 → T-1Countdown OwnerToolkit · Rehearsal Script, Go-No-Go Gate
Adoption, change impact, stakeholders, commsFrom T-27Adoption NavigatorToolkit · four sheets
RAID, countdown board, hypercare log, T-Plus backlog, KPIsT-27 → T+30Flight LeadToolkit · five sheets

Using the Project Plans workbook

  1. Enter the go-live date and public holidays on the Setup sheet — every task date is then calculated in working days from its T-day.
  2. Keep the sheets for the customer’s source systems; delete the others, and duplicate a sheet for any second instance (e.g. two company-code groups).
  3. Assign owners — the TRANXACT crew and the customer — and track status per task.
  4. Read the Dashboard daily: working days to go-live, tasks done and overdue per source, gate status across all sources.

The deployment checklist

Pre-flightDiscover (T-27→T-18)Configure (T-17→T-11)Gate T-11
Contract & audited revenueKey users in their rolesStructure & money configuredAll Configure-now done
Go-live date on the boardFit Ledger tagged & signedRoles & approvalsT-Plus list agreed
Countdown Owner & Flight LeadMigration scope per objectMaster data via ASKM1 mapping signed
Tenant provisioned, SSOChange impact first passIntegrations & queuesTest plan complete
Legacy extract accessComms T-27 & T-18 sentConfiguration checks passedRehearsal roles known
Cutover (T-10→T-3)Rehearsal (T-2→T-1)Go-live (T-0)Hypercare (T+1→T+30)
M1 and M2 loadedReal day scriptedLegacy frozen & read-onlyDaily exception standup
Zero TB delta, sub-ledgers tieEvery T+1 user took partFinal load reconciled & signedFirst month-end closed
Integration & role testsResults match legacyProduction endpoints liveKPIs recorded
Dry run timed in windowFix list closed same dayUsers enabled, comms sentT-Plus wave 1 planned
Continuity check doneGO recorded with evidenceFirst invoice postedHypercare exit signed

What day do we go live? The question was never how long the project will take. Agree the date and name the Countdown Owner; complete pre-flight and start the clock at T-27; copy the source-system sheets you need; run every standup from the board; let the rehearsal decide.

Values marked proposed default are the methodology’s recommended starting points. Confirm each one per engagement; the contract, order form and SLA prevail.