Manufacturing › Plan
Material Availability
Whether an order can be made: what is on hand, what is already promised to somebody else, what is on its way, and what has to be bought.
In Manufacturing → Plan · 3 screens
RecordsAvailability ChecksThe question “can this be made”, asked of a sales order or a configuration, and the answer as it stood at that moment. Kept as a document because the shortage it found is what a requisition was raised from.OpenViewAvailability · LinesLine by line: what is on hand, what of that is already promised, what is on order, what is on a production order, and what is genuinely short. The four are kept apart because “we have none” and “it is all promised elsewhere” want different things done about them.OpenRecordsMaterial ReservationsStock promised to one order and no longer offered to another. Without a reservation two orders are both told the same bar is available, and the second one finds out on the shop floor.Open
Columns, fields and actions
| Screen | Kind | What it is | Columns | Fields | Actions |
|---|---|---|---|---|---|
| Availability Checks | List | The question “can this be made”, asked of a sales order or a configuration, and the answer as it stood at that moment. Kept as a document because the shortage it found is what a requisition was raised from. | 14 | 7 | 0 |
| Availability · Lines | Read-only list | Line by line: what is on hand, what of that is already promised, what is on order, what is on a production order, and what is genuinely short. The four are kept apart because “we have none” and “it is all promised elsewhere” want different things done about them. | 16 | 0 | 0 |
| Material Reservations | List | Stock promised to one order and no longer offered to another. Without a reservation two orders are both told the same bar is available, and the second one finds out on the shop floor. | 14 | 9 | 2 |