Master Production Schedules

What the plant commits to finish, period by period. The consumption rule is the whole point: a company that adds forecast to orders builds everything twice.

Where to find it

  1. Module: Manufacturing
  2. Group: Plan
  3. Section: Master Scheduling
  4. Screen: Master Production Schedules

Address in the console: /mfg/master-schedules

List · 11 columns · 17 fields on its form · 3 of them required · 4 actions

What the list shows

These are the columns of the list, in the order they are drawn. Any of them can be sorted on, filtered on, hidden, or exported.

ColumnKindField name
ScheduleCodeschedule_no
NameTextname
ItemCodeitem_no
BucketStatusbucket
FromDatehorizon_from
ToDatehorizon_to
ConsumptionStatusconsumption_rule
PeriodsNumberperiod_count
ScheduledNumberscheduled_quantity
NegativeNumbernegative_periods
StatusStatusstatus

The form

What is asked for when a record is created here. Required fields are marked; a choice drawn from a configuration list is one an administrator can extend without a release.

FieldTypeChoicesNotes
Name required Text
Item Choice Looked up from existing records
Product family Text For a plant-level schedule covering a family rather than one item.
Warehouse Choice Looked up from existing records
Demand plan Choice Looked up from existing records Where the forecast comes from, so a change to it is traceable into the schedule rather than retyped.
Bucket Choice week, day, month
Horizon from required Date
Horizon to required Date
Demand time fence (days) Number Inside it the forecast is ignored and only real orders count.
Planning time fence (days) Number Inside it the system may not move supply on its own. Without it, every re-run reschedules the job on the machine.
Consumption rule Choice consume_forward, consume_backward, consume_both, greater_of, sum
Consume forward (days) Number
Consume backward (days) Number
Safety stock Number
Target days of supply Number
Planner Choice Looked up from existing records
Notes Long text

What you can do here

Periods

On each row of the list.

Build primary

On each row of the list. Offered only on records where it applies.

Asks for confirmation: Rebuild the grid from the forecast, the order book and existing supply? Any quantity typed over a period is replaced.

Rough-cut capacity

On each row of the list.

Asks for confirmation: Run the schedule against the bill of resources? Refused if the item has none — rough-cut needs three or four critical resources, not the whole routing.

Firm

On each row of the list. Offered only on records where it applies.

Firm the schedule

Asks for: Reason, if firming over a negative period

The rules that apply here

Everything on this screen obeys the platform rules rather than rules of its own. The ones worth knowing before you use it: