Item time fences in material requirements planning

The demand, planning and release time fences on an item’s planning record are now honoured by the planner, in addition to the plan’s own frozen window.

  • Planning time fence: nothing new may start inside it. A proposal needed sooner is moved to the first day after the fence and an exception says so.
  • Demand time fence: inside it the forecast is ignored and only real orders drive the plan.
  • Release time fence: proposals inside it are the ones the Run MRP and firm rule firms, instead of the rule’s own days.

An item with no fences plans exactly as before.