Project Plan: the schedule, previews and project baselines

Since release 20261106c the Project Plan is interactive: drag bars on the Schedule, see the effect before it is saved, link activities, work on the Board, Calendar and Network, and save, approve and compare baselines.

Accounting › Revenue & Projects › Projects & Portfolios › Project Plan. Since release 20261106c it is interactive and has the tabs Work breakdown, Schedule, Milestones, Board, Calendar, Network and Baselines. Durations count working days on the project’s or the company’s calendar.

Schedule (the Gantt chart)

  • Drag a bar to move it. Drag its right edge to change its length.
  • Drag the dot at its end onto another bar to link them: choose finish-to-start, start-to-start, finish-to-finish or start-to-finish, and a lag in working days (negative for a lead).
  • The current baseline appears as a thin grey bar under each bar.

Preview before saving

Nothing is saved by a drag. A preview shows which activities and milestones move, the project finish before and after, the critical path gained and lost, and anyone booked twice. Press Apply to save or Cancel to drop it. Undo and Redo undo and redo your saved changes in this session.

Keyboard

  • Tab to a bar. The arrow keys move it a day, Shift with the arrow keys changes its length, and Page Up and Page Down move it a week.
  • Enter previews the move. Enter on a bar you have not moved, or a double-click, opens its dates and links.
  • Press L, then Enter on another bar, to link the two.

Recalculate and the critical path

  • Recalculate works the schedule out on working days: the project’s Working calendar if one is set (a new field on the project), otherwise the company’s holiday calendar.
  • Critical activities are marked critical. Activities are marked near-critical when their float is at most the days set in Runtime Settings › Projects.

Milestones, Board, Work breakdown, Calendar and Network

  • Milestones: a milestone can name the activity that achieves it (Achieved by activity). Its forecast then follows that activity, and its planned date acts as the activity’s deadline.
  • Board: drag a card to another column, or use Move to, to change its status.
  • Work breakdown: dates, cost and progress roll up from the activities. Click a name, budget or progress figure to edit it. Drag a row onto another, or use Move under, to change its parent.
  • Calendar: drag an activity to another day to move its start; it is previewed first.
  • Network: activities as boxes with their early and late dates and float, and a list of open ends, negative float and constrained activities.

Project baselines

  1. On Baselines, save the current forecast as a baseline for approval.
  2. Someone else who holds Accounting › Project Baselines approves or refuses it. You cannot approve your own.
  3. Replacing a baseline needs a reason.
  4. Compare lists what moved since the baseline, and by how many working days.

A Schedule performance (SPI) tile sits next to Cost performance.

See Approve and release a project, and Labour in the ledger and the payroll true-up.