Since release 20261114 Run MRP › Firm suggestions on a sales order copies the BOM and process adjustments made on the order line onto the new production order, unless the production order covers more than one line or an adjustment is below the product’s own level.

When you run Run MRP › Firm suggestions on a sales order (CRM › Order to Cash › Selling › Sales Orders, open the order), the BOM and process adjustments made on the order line are copied onto the new production order.

When nothing is copied

  • The production order covers more than one order line, or
  • an adjustment changes a part below the product’s own level.

Then the production order keeps its standard components and operations, and the message lists the adjustments to make by hand under Manufacturing › Make › Production › Production Orders.

See also Adjusting the bill of material and process for one line.