TRANXACT.AI मदद

Liquidated damages for late delivery

Since release 20261113 a purchase or sales order can carry liquidated damages (LD): a percentage of the order value for every period of delay, up to a cap. Set the LD condition and say which orders carry it; the order works out what is due, prints the clause, and can waive it or raise the credit note.

Liquidated damages (LD) are a penalty for delivering late: a percentage of the order value for every week (or day, or month) of delay, up to a cap. The standard LD is 0.5% a week, at most 5%.

Example: an order of 10,00,000 due on 1 Nov and delivered on 15 Dec is 6 weeks late: 3%, which is 30,000.

Set it up

  1. Go to CRM › Customers › Pricing Procedures › Pricing Condition Types for customers, or Supply Chain › Purchasing › Purchase Charges › Purchase Charge Conditions for suppliers, and open LD.
  2. Check the rate per period and the period; the cap; Taken on (the whole order’s value, or only the value of the goods delivered late); Part of a period (completed periods only, or every period begun counts); the grace days; the GL accounts; and the clause printed on the order. Leave the clause empty for the standard wording.
  3. Say which orders carry LD: add a condition record of LD on CRM › Customers › Pricing Procedures › Pricing Condition Records (customers) or Supply Chain › Purchasing › Purchase Charges › Purchase Charge Records (suppliers), with the rate per period (0.5), for a supplier, a customer, a customer group, an item, an item category, or every order.

Without a condition record, no order carries LD.

On the order

  • A new purchase order (Supply Chain › Purchasing › Requisitions & Orders › Purchase Orders) or sales order (CRM › Order to Cash › Selling › Sales Orders) picks up its LD terms from the records.
  • Change them with Edit: the LD type, rate, period, cap, what it is taken on, part of a period and grace days. Once goods have been received or issued, the terms are fixed.
  • The Liquidated damages tab shows each line and delivery: the contractual date (the line’s need-by or requested date, else the order’s), the actual date (goods receipt or goods issue), days and periods late, the percentage, the amount, and what the cap cut off.
  • Goods still to come and already late are counted up to today.
  • The printed purchase order and order confirmation carry the LD clause with the order’s own figures.

Waive or settle

  1. Waive liquidated damages: enter the amount and why. The reason is kept on the order and in the audit log.
  2. Raise LD credit note creates a draft supplier credit note (purchase order) or customer credit note (sales order) for what is due. Post it from Accounting › Working Capital › Payables & Receivables › AP Credit / Debit Memos or Accounting › Working Capital › Payables & Receivables › AR Credit / Debit Memos.

Who can

Waiving needs the role grant Liquidated Damages, Change, on Platform › Access & Security › Access › Roles. Since release 20261114 waiving, raising and posting the LD credit note need “Liquidated Damages: Waive and Post” (the Financial Controller by default), LD is taken by default on the net value of the goods delivered late, and the LD note carries no tax unless you choose a tax code. See Liquidated damages: tax, base and who settles them.